ou are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value and actual value. That means the project is _____ schedule and _____ budget.

Answers

Answer 1

Answer:

B. ahead of; under

Explanation:

Earned value analysis is the process to check the status of the project and the analysis, evaluation is to be done. It can be done between the earned value with the actual cost incurred and with the planned value

Here Planned value refers to the value i.e. to be permitted and to be completed within the prescribed time. Here earned value is compared with the planned value to check the variance schedule of the project

Here the actual value is the value that is actually spent or incurred till date. Here the earned value compared with the actual value so that any variance related to cost could be checked

And, the earned value is the value of the work completed till date. It could be in terms of costing and scheduling.

So if the earned value is more than the planned value and the actual value so the project is ahead and it is under budget

hence, option B is correct


Related Questions

With this in mind, are accountants ethically obligated to report financial information accurately? Does reporting using the generally accepted accounting principles imply accuracy? What are some potential consequences for an external analyst if a company provides inaccurate or misleading financial statements?

Answers

Answer:

1. Accountants are ethically obligated to report financial information accurately

2. Reporting using the generally accepted accounting principles underscore on accuracy

3. Loss of confidence, lack of trust on the accounting team, a huge strain on their professional judgement and ethics.

Explanation:

1. Financial information in itself possesses some vital characteristics. One of these is the accuracy of the financial information. As the handler of financial activities, accountants are therefore saddled and ethically obligated to present and prepare their information accurately. This is so as to reflect the true picture of the going in the organization.

2. Reporting using GAAP - Generally Accepted Accounting Principles, seeks to converge the presentation of financial reports and statements on the basis of accuracy. Thus, reliability and relevance are ultimately the foremost objectives of these principles. I therefore have no doubt its usage conveys accuracy of reports.

3. Loss of confidence - financial reports through which the external analyst worked upon are often prepared by the internal staffs. The implication of a wrong and misleading reports from the company is an erosion of confidence on the credibility, reliability and competence of company's preparers of reports.

Lack of trust - The point above ultimately impacts on the level of trust placed on the accuracy, reliability and relevance of financial reports.

Professional Judgement and Ethics - The conducts of the company in presenting a wrong report throws the analyst into an ethnical dilemma, and a huge professional strain. This is not in line with best practices.

Problem 5-13 Comprehensive Problem; Second Production Department-Weighted-Average Method [LO5-2, LO5-3, LO5-4, LO5-5] Old Country Links, Inc., produces sausages in three production departments—Mixing, Casing and Curing, and Packaging. In the Mixing Department, meats are prepared and ground and then mixed with spices. The spiced meat mixture is then transferred to the Casing and Curing Department, where the mixture is force-fed into casings and then hung and cured in climate-controlled smoking chambers. In the Packaging Department, the cured sausages are sorted, packed, and labeled. The company uses the weighted-average method in its process costing system. Data for September for the Casing and Curing Department follow:

Answers

Question Completion:

Data for September for the Casing and Curing Department follow:

                                                                        Percent Completed

                                                           Units  Mixing   Materials  Conversion

Work in process inventory, Sept. 1       7      100%         60%         50%

Work in process inventory, Sept 30    7      100%          20%         10%

Costs:

                                                             Mixing     Materials    Conversion

Work in process inventory, Sept. 1    $13,006          $112           $11,193

Costs added during September     $128,404     $11,852         $110,310

Mixing cost represents the costs of the spiced meat mixture transferred in from the Mixing Department. The spiced meat mixture is processed in the Casing and Curing Department in batches; each unit in the above table is a batch and one batch of spiced meat mixture produces a set amount of sausages that are passed on to the Packaging Department. During September, 72 batches (i.e., units) were completed and transferred to the Packaging Department.

Answer:

Old Country Links, Inc.

Required:

1. Determine the Casing and Curing Department's equivalent units of production for mixing, materials, and conversion for the month of September:

                                                       Mixing     Materials    Conversion

Equivalent units of production:

Ending Work in process                     7                1.4               0.7

Completed and transferred out       72              72               72

Equivalent units                                79             73.4             72.7

2. Compute the Casing and Curing Department's cost per equivalent unit for mixing, materials, and conversion for the month of September.

                                                       Mixing     Materials    Conversion

Total costs of production           $141,410       $11,964       $114,503

Equivalent units                                79              73.4             72.7

Cost per equivalent unit:              $1,790           $163          $1,575

3. Compute the Casing and Curing Department's cost of ending work in process inventory for mixing, materials, conversion, and in total for September.

                                               Mixing     Materials    Conversion   Total Cost

Cost per equivalent unit:        $1,790      $163          $1,575

Equivalent units of Ending WIP   7             1.4               0.7

Ending WIP                           $12,530         $228        $1,103         $13,861

4. Compute the Casing and Curing Department's cost of units transferred out to the Packaging Department for mixing, materials, conversion, and in total for September.

                                           Mixing     Materials    Conversion   Total Cost

Cost per equivalent unit:   $1,790         $163          $1,575

Transferred out                      72              72                72

Cost transferred out      $128,880     $11,736        $113,400    $254,016

5. Prepare a cost reconciliation report for the Casing and Curing Department for September.

Costs to be accounted for:

Cost of beginning WIP                     $17,311

Costs added to production          250,566

Total costs to be accounted for $267,877

Costs accounted for:

Cost of Ending WIP                      $13,861

Cost of units completed

        & transferred out             $254,016

Total costs accounted for        $267,877

Explanation:

a) Total Costs of production:

Costs:

                                                             Mixing     Materials    Conversion

Work in process inventory, Sept. 1    $13,006          $112           $4,193

Costs added during September     $128,404     $11,852        $110,310

Total costs of production                  $141,410     $11,964       $114,503

b) Equivalent unit of Ending WIP and beginning WIP

Ending Work in process        7 (7 x 100%)      1.4 (7 x 20%)    0.7 (7 x 10%)

Beginning Work in process  7 (7 x 100%)      4.2 (7 x 60%)    3.5 (7 x 50%)

c) In using the weighted-average method, Old Country Links, Inc. calculates the equivalent units of production by adding the units transferred to the Packaging Department during the period and the equivalent units in the Casing and Curing Department's ending work in process inventory.  Old Country Links, Inc. uses one Work in Process account to accumulate costs for all jobs in each department.

Some customers are __________, caring about new developments in their category and seeking out new products.

Answers

Answer:

Early adopters

Explanation:

Early adopters define to adopt a new product or technology introduced in the market place for the first customers or the new customers

Here the product or technology is the first time introduced in the market with a lot of expectations which could be in terms of sales, revenues, trust, satisfaction, etc

Therefore in the given situation, the early adopters should be chosen for the new developments in the products category

Suppose that​ Firm A and Firm B are independently deciding whether to sell at the low price or a higher price. The payoff matrix below shows the profits per year for each company resulting from the two price options. a. Does​ Firm A have a dominant strategy? The dominant strategy for Firm A is a low price. No, there is no dominant strategy for Firm A. The dominant strategy for Firm A is a high price.

Answers

Answer: No, there is no dominant strategy for Firm A.

Explanation:

Dominant strategies would refer to those that a Firm can take and still have a better payoff regardless of what the other Firm/player chooses. From the above, there is no dominant strategy for Firm A because there is no single strategy that they can follow that will maximise payoff regardless of what B does.

For instance, if Firm A were to charge a lower price, and Firm B charged a higher price, Firm A would make less than Firm B at $2 million. They make less regardless of any decision they make.

Timmy Company's comparative balance sheet at January 31, 2017, and 2016. reports the following (in millions):
Three situations about Timmy Company's issuance of stock and declaration and payment of dividends during the year ended January 31, 2017.
follow. Read the requirements.
Begin by reviewing the labels for the change in stockholders' equity and then enter the amounts for each situation. (Enter an amount in each input area. Input a "0" when there is no amount to be entered. Enter amount millions. Use a minus sign or parentheses when entering net losses or numbers to be subtracted.)
Total stockholders' equity, January 31, 2016
Add: Issuance of stock
Net income
Less: Dividends declared
Net loss
Total stockholders' equity, January 31, 2017
For each situation, use the accounting equation and the statement of retained earnings to compute the amount of Timmy's net income or net loss during the year ended January 31 2017.
1. Timmy issued $13 million of stock and declared no dividends.
2. Timmy issued no stock but declared dividends of $17 million.
3. Timmy issued $20 million of stock and declared dividends of $27 million.

Answers

Answer:

The Accounting Equation states that;

Assets = Liabilities + Equity

Equity as at 2016 = Assets - Liabilities

= 50 - 13

= $37 million

Equity as at 2017 = Assets - Liabilities

= 77 - 18

= $59 million

1. Timmy issued $13 million of stock and declared no dividends.

The Net Income ( loss) will be the figure that gives the Statement of Equity a figure of $59 million.

Net Income = Total stockholders' equity, January 31, 2017 - Total stockholders' equity, January 31, 2016  - Issuance of stock

= 59 - 37 - 13

= $9 million

Total stockholders' equity, January 31, 2016  ................ 37

Add: Issuance of stock ......................................................... 13

Net income  ......................................................................9

Less: Dividends declared......................................................0

Net loss.......................................................................................0

Total stockholders' equity, January 31, 2017...................59

2. Timmy issued no stock but declared dividends of $17 million.

Net Income (loss) = Total stockholders' equity, January 31, 2017 - Total stockholders' equity, January 31, 2016  + Dividends Declared

= 59 - 37 + 17

= $39 million

Total stockholders' equity, January 31, 2016  ................ 37

Add: Issuance of stock ......................................................... 0

Net income  ......................................................................39

Less: Dividends declared......................................................(17)

Net loss.......................................................................................0

Total stockholders' equity, January 31, 2017...................59

3. Timmy issued $20 million of stock and declared dividends of $27 million.

Net Income (loss) = Total stockholders' equity, January 31, 2017 - Total stockholders' equity, January 31, 2016  + Dividends Declared -  Issuance of stock

= 59 - 37 + 27 - 20

= $29 million

Total stockholders' equity, January 31, 2016  ................ 37

Add: Issuance of stock ......................................................... 20

Net income  ......................................................................29

Less: Dividends declared......................................................(27)

Net loss.......................................................................................0

Total stockholders' equity, January 31, 2017...................59

The following information describes a​ company's usage of direct labor in a recent​ period: Actual direct labor hours used Actual rate per hour Standard rate per hour Standard hours for units produced How much is the direct labor efficiency​ variance?

Answers

Answer: a) $26,000 Favorable

Explanation:

The Direct labor efficiency variance checks the how well staff are actually utilizing labor hours vs how they are expected to be utilizing it and is calculated by the formula;

Direct Labor Efficiency variance = (Standard hours – Actual hours) x Standard rate

Direct Labor Efficiency variance = ( 43,000 - 41,000 ) * 13

Direct Labor Efficiency variance = $26,000

As the Standard hours are higher than the actual hours used, this is considered a Favorable Variance.

Panther Co. had a quality-assurance warranty liability of $356,000 at the beginning of 2018 and $302,000 at the end of 2018. Warranty expense is based on 5% of sales, which were $55 million for the year. What were the warranty expenditures for 2018

Answers

Answer:

$2,804,000

Explanation:

Panther corporation has a quality assurance liability of $356,000 at thr start of 2018

They also had a quality assurance liability of $302,000 at the end of 2018

Warranty expense is 5% of the total sales which was $55 million for the year

= 5/100 × 55,000,000

= 0.05×55,000,000

= 2,750,000

Therefore, the warranty expenditures for 2018 can be calculated as follows

=$356,000+$2,750,000-$302,000

= $3,106,000-$302,000

= $2,804,000

Hence the warranty expenditures for 2018 is $2,804,000

What do you think are the possible major tensions that exist when a pharmaceutical firm forms an alliance with a biotechnology firm?

Answers

Answer:

The answer is below

Explanation:

Possible major tensions that exist when a pharmaceutical firm forms an alliance with a biotechnology firm are the following amongst others:

1. There is high competition from other alliances between different pharmaceutical and biotechnological firms:

In recent times, several pharmaceutical and biotechnological firms are establishing partnerships with a high probability of success, in the development of drugs and marketing. This has led to more competition and which made firms to be under immense pressure to formulate new products.

2. More public attention of the business methods and profits by the government:

Many policies and regulations regarding the healthcare sectors are designed to checkmate corrupt practices in the health industry. Thus, such alliances need to accept such regulations and operate. Otherwise, this may result in the cancellation of the permission of the operation.

3. The interdependence of the firms involved:

Both firms might find it difficult to operate most specifically at the beginning, as there will be little tension when it comes to management decisions and operation.

Thaddeus Conway Corporation reported the following activity during the current year:
Gross Profit $69,000,000
Operating Expenses ($57,000,000)
Captial Gains $17,000,000
Capital Losses ($24,000,000)
The corporation's tax liability amounts to:________
a) some other amount
b) $1,050,000
c) $6,090,000
d) $2,520,000

Answers

Answer:

$2,520,000

Explanation:

Capital gains of $17,000,000 will setted off against the loss of 24,000,000 and the remaining 7,000,000 will be carried forward for the next year.

DATA

Gross Profit               = $69,000,000

Operating Expenses = ($57,000,000)

Captial Gains             = $17,000,000

Capital Losses            = ($24,000,000)

Tax Rate  = 21%

Calculation

Taxable Income = $69,000,000 - $57,000,000 = $12,000,000

Tax Liability = Taxable Income * Tax Rate  

Tax Liability = $12,000,000 * 21%

Tax Liability = $2,520,000

NOTE: Any Capital losses of the corporation can be set off against the Capital gains of the year

You open an individual retirement account (IRA) with a mutual fund and contribute $1,000 into the account each year. How much will be in the account after 20 years if the investment earns 7% annually

Answers

Answer:

The worth of the investment after 20 years = $40,995.5  

Explanation:

The equal annual deposit can be worked out using the future value of an ordinary annuity formula.

The worth of the investment after 20 years can be worked out using the future value of an ordinary annuity.

An an annuity is a series of equal cash flows receivable or payable  for certain number years.

Future Value of an ordinary annuity (FVOA). The represents the total sum of that would accrue where a series of annual cash flow (each occurring at the end of the year) is compounded at a particular rate. It can be determined as:  

FV= A × ( (1+r)^n - 1)/r).  

FV- Future value

A- annual cash flow

R- rate of interest

n-number of years

FV - ?

A- 100

r- 7%

n- 20

FV = 1,000× (1.07^20 - 1)/0.07 =  40,995.5  

The worth of the investment after 20 years = $40,995.5  

Job 652 was recently completed. The following data have been recorded on its job cost sheet:_______.
Direct materials $ 65,400
Direct labor-hours 1,236 DLHs
Direct labor wage rate $ 15 per DLH
Number of units completed 4,800 units
The company applies manufacturing overhead on the basis of direct labor-hours. The predetermined overhead rate is $35 per direct labor-hour.
Required:
Compute the unit product cost that woild appear on the job cost sheet for this job. (Round your answer to 2 decimal places.)
Unit product cost

Answers

Answer:

Unit product cost = $26.50

Explanation:

The computation of the unit product cost is shown below:

As we know that

Unit product cost = Total cost ÷ number of units completed

where,

Total cost is

= Direct materials + direct labor + manufacturing overhead

= $65,400 + 1,236 × $15 + 1,236 × $35

= $65,400 + $18,540 + $43,260

= $127,200

And, the number of units completed is 4,800 units

So, the unit product cost is

= $127,200 ÷ 4,800 units

= $26.50

Suppose a local hardware store has explicit costs of $2 million per year and implicit costs of $44,000 per year. If the store earned an economic profit of $50,000 last year, this means that the store's accounting profit equaled:

Answers

Answer:

$94,000

Explanation:

A local hardware store has explicit cost of $2 million per year

The implicit costs are $44,000 per year

The store earned an economic profit of $50,000 last year

Therefore, the store's accounting profit can be calculated as follows

Accounting profit = Implicit costs + economic profit

= $44,000 + $50,000

= $94,000

Hence the store's accounting profit is $94,000

Since entrepreneurs are starting new businesses, experience gained from working for an established business isn't particularly helpful.a) trueb) false

Answers

Answer:

False

Explanation:

Entrepreneurs who are starting new businesses, can use experiences gained from working for an established business. This is particularly helpful. It helps them to avoid certain mistakes and pitfalls that they might have noticed or observed in the established company they are coming from.

Also, it enables them to practice certain business ethics they learnt from the established firms they are coming from.

2.Privacy goes hand in hand with security, but many of the activities of information security analysts seem to be an invasion of privacy. Discuss how employers can justify the use of tools, such as Encase by Guidance Software.

Answers

Answer And Explanation:

Privacy and security do work in hand in hand and complement each other in ensuring information security .By privacy we mean data that should not be available to the public and is only privy to individuals or organizations that can be attributed to ownership or use of the data. Private data could be such things as documents, photos, emails or tax returns of a person. security on the other hand are measures taken both technological or otherwise to protect the data and only give access to who should have access to the data example the owner of the photos. More specifically, security on this sense measures or comprises how secure our data is from external and undesired/unauthorized access bordering on such things as terms of network security,hardware security or data security.

Now for a security analyst to be able to protect your data, there is need to have access to your data and be able to keep track of data stored and packet flow. This could be argued to contradict privacy of data but it can be concluded that the security analyst cannot protect your data if he is not able to scan and keep track of data and therefore have access to the data.

It therefore goes to say that there must be a balance between security and privacy as they are both complementary. Encase by Guidance Software is a good example of a security software that somewhat compromises security to achieve maximum security. It is known to permeate all private data of employees in organization in the bid to keep track and protect against any malicious attacks or illegal activity. In other words, while it may seem like it violates privacy, it balances it with full protection

Assume that the multiplier in the Chinese economy is 3 and autonomous investment expenditures increase by $100. The Chinese government has a budget deficit of $100 and the income tax rate is 30 percent. The increase in autonomous investment expenditures will:
A. increase equilibrium income by $300 and cause the budget deficit to decrease by $90.
B. increase equilibrium income by $300 and cause the budget deficit to decrease by $100.
C. increase equilibrium income by $300 and cause the budget deficit to increase by $100.
D. increase equilibrium income by $300 and cause the budget deficit to increase by $90.

Answers

Answer:

A. increase equilibrium income by $300 and cause the budget deficit to decrease by $90.

Explanation:

Change in income = Multiplier * Change in investment

Change in income =  $3 * 100

Change in income = $300

So, Income tax increase by = $300 * 0.3

= $90. Government expenditure is unchanged. So, Budget deficit (G-T) decreases by $90.

Electronics Company A is recognized as the world leader in the production of radios. They
control more than 75% of the radio market, but the market is slowly shrinking. The company also
makes several high-quality audio products, including CD players. The market for CD players is
growing, and currently the company cannot make enough to meet the demand. What choice
should the company make? What is the opportunity cost? Explain your reasoning,

Answers

Answer:

There comes a time when every company must make a decision to evolve because the products that they offer will always become obsolete at some point in the future. This is simply because humans will always strive to make processes more efficient.

Electronics Company A is a leader in the radio market but that market is shrinking. There is a new revenue stream however and that market is growing.

The decision that they should make is to reduce the amount of facilities that are dedicated to radios and channel it to the production of CD players so that they may gain dominance there before the market becomes saturated. Had Kodak have done this when digital cameras were on the rise, their fall from grace might not have happened at all.

The Opportunity Cost of this however is that they may lose dominance in the radio industry which is only slowly declining meaning that there are still profits to be made. The keyword however is that the market is declining. They should therefore evolve and move to an industry that is on the up and up which is the CD player.

Failure to do this would mean that they would become another Kodak or Blockbuster.

Phyllis Stintson needs to decide whether to start a campaign against deforestation in Indonesia. Though her research team has provided substantial information on the high feasibility of the project, Stintson does not go ahead with the project. Stintson's decision is most likely influenced by which of the following if she made the decision by drawing unconscious references from several different experiences in the past?
A) optimization
B) intuition
C) fundamental attribution error
D) framing effect
E) anchoring bias

Answers

Answer:

B) intuition

Explanation:

Analyzing the scenario above, it is clear that Phyllis Stintson performed the decision-making process according to her intuition.

It is possible to perceive the use of intuition as the question provides information that he made the decision by drawing unconscious references from several different experiences in the past.

Intuition can be an important skill for leaders, who need to make decisions that are increasingly quick and important for the success of an organization, so it is important that a leader's self-awareness is a valued characteristic, because from self-awareness the leader has greater emotional control over his experiences, his intuition, his knowledge and other essential characteristics which will be useful to base an important decision-making process.

In which situations is a broker/seller NOT required to provide a written disclosure regarding the broker's license status?

Answers

Answer: when the broker is selling property for the broker's sister

Explanation:

The situations in which a broker or seller is not required to provide a written disclosure regarding the broker's license status is when the broker is selling property for the broker's sister.

It should be noted that license holders

that wants to either purchase or sell a property on their behalf or for a relation should disclose that they are licensed and this should be done in writing.

A woman worked for 30 years before retiring. At the end of the first year of employment she deposited 5000 into an account for her retirement. At the end of each subsequent year of employment, she deposited 3% more than the prior year. The woman made a total of 30 deposits. She will withdraw 50,000 at the beginning of the first year of retirement and will make annual withdrawals at the beginning of each subsequent year for a total of 30 withdrawals. Each of these subsequent withdrawals will be 3% more than the prior year. The final withdrawal depletes the account. The account earns a constant annual effective interest rate. Calculate the account balance after the final deposit and before the first withdrawal.

Answers

Answer:

$797,837

Explanation:

the first withdrawal is $50,000

the second is $51,500

and so on...

the formula that used to solve the interest rate earned by the annuity is:

$50,000 x {[(1 + i)³⁰ - (1 + 3%)³⁰] / [(1 + i)³⁰ x (i - 3%)]} x (1 + i) = $5,000 x {[(1 + i)³⁰ - (1 + 3%)³⁰] / (i - 3%)}

we start to simplify the equation by cancelling  {[(1 + i)³⁰ - (1 + 3%)³⁰] / (i - 3%)}

[$50,000 x (1 + i)] / (1 + i)³⁰ = $5,000

now we cancel $5,000 on each side:

[10 x (1 + i)] / (1 + i)³⁰ = 1

now lets take away (1 + i):

10 / (1 + i)²⁹ = 1

things get a little bit more simple now:

10 = (1 + i)²⁹

²⁹√10 = ²⁹√(1 + i)²⁹

1.082636734 = 1 + i

i = 1.082636734 - 1 = 0.082636734 = 8.2636734%

now we replace i in any equation:

= $50,000 x {[(1 + 0.082636734)³⁰ - 1.03³⁰] / [(1 + 0.082636734)³⁰ x (0.082636734 - 0.03)]} x (1 + 0.082636734)

= $50,000 x  {[10.82636738 - 2.427262471] / [10.82636738 x 0.052636734]} x (1 + 0.082636734)

= $50,000 x  {8.399104909 / 0.56986462} x (1.082636734)

= $50,000 x 14.73877236 x 1.082636734

= $797,837

Norek Corp. owned 70% of the voting common stock of Thelma Co. On January 2, 2018, Thelma sold a parcel of land to Norek. The land had a book value of $42,000 and was sold to Norek for $75,000. Thelma's reported net income for 2018 was $200,000. What is the non-controlling interest's share of Thelma's net income?

Answers

Answer:

$50,100

Explanation:

The computation of the non-controlling interest share is shown below:

= {Net income - (Sale value - book value)} × non owning percentage

= {$200,000 - ($75,000 - $42,000)} × 0.30

= ($200,000 - $33,000) × 0.30

= $50,100

Hence, the non controlling interest share of net income is $50,100 and the same is to be considered

Voltanis Corp. has preferred stock outstanding that will pay an annual dividend of $2.85 every year in perpetuity. If the stock currently sells for $92.87 per share, what is the required return?

Answers

Answer:

3.07%

Explanation:

Required return is a financial term that describes the least return an individual or investor hopes to obtain by investing in a particular project. This can be derived by dividing expected annual dividend of stock with current rate of stocks, then multiply by 100

Hence, in this case, the expected annual dividend of stock is $2.85

The current rate of stock per share is $92.87

Therefore, the required return is $2.85/$92.87 = 0.0307 * 100

=> 3.07%

Hence, the final answer is 3.07%.

A project with an initial cost of $51,400 is expected to generate annual cash flows of $16,910 for the next 5 years. What is the project's internal rate of return

Answers

Answer:

19.27%

Explanation:

Internal rate of return is the discount rate that equates the after tax cash flows from an investment to the amount invested

IRR can be calculated with a financial calculator  

Cash flow in year 0 =  $-51,400

Cash flow each year from year 1 to 5 = $16,910

IRR = 19.27%

To find the IRR using a financial calculator:

1. Input the cash flow values by pressing the CF button. After inputting the value, press enter and the arrow facing a downward direction.

2. After inputting all the cash flows, press the IRR button and then press the compute button.  

The manager at​ Tom's Taxidermy expects to sell units at each unit. In order for the manager to​ breakeven, the manager must sell units. What is the margin of safety in​ dollars?

Answers

The manager at​ Tom's Taxidermy expects to sell 900 units at​ $80 each unit. In order for the manager to​ breakeven, the manager must sell 100 units. What is the margin of safety in​ dollars?

Answer:

$64,000

Explanation:

Given that, the margin of safety is a term that describes the disparity between the actual sales volume and the breakeven volume.

In this case, Tom's Taxidermy expects to sell 9,00 units at $80 each and their breakeven volume is 100 units, the margin of sales, in dollars, is:

MS = ( 900 - 100) * $80

MS = 800 * $80

= $64,000

Therefore, the right answer as Margin of Safety in dollars = $64,000

10 years ago, the City of Melrose issued $3,000,000 of 8% coupon, 30-year, semiannual payment, tax-exempt muni bonds. The bonds had 10 years of call protection, but now the bonds can be called if the city chooses to do so. The call premium would be 6% of the face amount. New 20-year, 6%, semiannual payment bonds can be sold at par, but flotation costs on this issue would be 2% of the amount of bonds sold. What is the net present value of the refunding? Note that cities pay no income taxes, hence taxes are not relevant.

Answers

Answer:

the net present value of the refunding = $453,443

Explanation:

Given that:

Amount issued by  City of  Melrose = $3,000,000

Old rate of coupon = 8%

Period (years) = 20

Call premium = 6%

New rate coupon = 6%

Flotation cost = 2%

For the cost of refunding ; we have:

Call premium = 6% × $3,000,000

Call premium = 0.06  × $3,000,000

Call premium = $180000

Floatation cost = 2%  × $3,000,000

Floatation cost = 0.02 × $3,000,000

Floatation cost = $60000

The total investment outlay = Call premium + Flotation cost

The total investment outlay = $180000  + $60000

The total investment outlay = $240000

However, the interest on the old bond per  6 months = (old coupon/2 )  × Amount issued

the interest on the old bond per  6 months = (8%/2)  ×  $3000000

the interest on the old bond per  6 months = (0.08/2) ×  $3000000

the interest on the old bond per  6 months = 0.04 ×  $3000000

the interest on the old bond per  6 months = $120000

the interest on the new bond per  6 months = (new coupon/2 )  × Amount issued

the interest on the new bond per  6 months = (6%/2)  ×  $3000000

the interest on the new bond per  6 months = (0.06/2) ×  $3000000

the interest on the new bond per  6 months = 0.03  ×  $3000000

the interest on the new bond per  6 months = $90000

Amount savings per 6 months = $120000 - $90000

Amount savings per 6 months = $30000

Finally, the present value for the savings = 30000 × PVIFA(0.03,40)

the present value for the savings = $693,443

Thus;

the net present value of the refunding = the present value for the savings - Cost of refunding

the net present value of the refunding = $693,443 - $240000

the net present value of the refunding = $453,443

You have a credit card with a balance of $12,100 and an APR of 17.5 percent compounded monthly. You have been making monthly payments of $235 per month, but you have received a substantial raise and will increase your monthly payments to $285 per month. How many months quicker will you be able to pay off the account

Answers

Answer:

you will pay off your debt in 32 months less

Explanation:

I prepared two amortization schedules:

if you pay $235, it will take you 99 months to pay off your debt

if you pay $285, it will take you 67 months to pay off your debt

You recently purchased a stock that is expected to earn 20 percent in a booming economy, 15 percent in a normal economy, and lose 2 percent in a recessionary economy. There is 21 percent probability of a boom, 72 percent chance of a normal economy, and 7 percent chance of a recession. What is your expected rate of return on this stock

Answers

Answer:

rE = 0.1486 or 14.86%

Explanation:

The expected rate of return of a stock is the mean return that is expected to be earned by the stock considering the different scenarios that can occur, the return in these scenarios and the probability of the occurrence of these scenarios. The formula for expected rate of return of stock is,

rE = pA * rA  +  pB * rB  +  ...  + pN * rN

Where,

pA, pB, ... represents the probability that scenario A, B and so on will occur or the probability of each scenariorA, rB, ... represents the return in scenario A, B and so on

rE = 0.21 * 0.2  +  0.72 * 0.15  +  0.07 * -0.02

rE = 0.1486 or 14.86%

The coupon rate on a debt issue is 6%. If the yield to maturity on the debt is 9%, what is the after-tax cost of debt in the weighted average cost of capital if the firm's tax rate is 34%

Answers

Answer:

Weighted average cost of capital= 5.94%

Explanation:

The cost of debt is the required rate of return payable to investors in the debt instruments of a company. These investors include providers of long term debt finance to the company.

The cost of debt finance can determined by working out the yield to maturity on debt with adjustment for tax.  

It is noteworthy that debt finance affords the company a tax savings advantage because interest expense incurred on the use of debt of are tax deductible expense.

After-tax cost of debt = (1- Tax rate) × before-tax cost of debt

Before tax cost of debt = 9%

Tax rate = 34%

After-tax cost of debt = (1-0.34) × 9% = 5.94%

After-tax cost of debt = 5.94%

Weighted average cost of capital= 5.94%

On June 1, Pina Colada Corp. borrows $111,000 from First Bank on a 6-month, $111,000, 8% note.

Required:
a. Prepare the entry on June 1.
b. Prepare the adjusting entry on June 30.
c. Prepare the entry at maturity (December 1), assuming monthly adjusting entries have been made through November 30.

Answers

Answer:

June 1

Cash $111,000 (debit)

Note Payable $111,000 (credit)

June 30

Interest expense $1,480 (debit)

Note Payable $1,480 (credit)

Nov 30

Note Payable $119,800 (debit)

Cash $119,800 (credit)

Explanation:

June 1

Recognize the Cash Asset received and a liability Note Payable

June 30

Interest for 1 month has accrued and this is calculated as :

Interest Expense = $111,000 × 8% × 1/6

                            = $1,480

Nov 30

Total Interest is capitalized to the Note Payable and the full amount is repaid

Total Interest = $111,000 × 8%

                      = $8,800

Ballon Amount = $111,000 + $8,800

                         = $119,800

The strategy that a firm chooses dictates such structural elements as the division of tasks, the need for integration of activities, and authority relationships within the organization. This implies that

Answers

Answer:

Structure follows strategy.

Explanation:

It is correct to say that the organizational structure follows strategy, that is, the organizational structure must be fully planned and developed according to what supports the tactical and operational action plans that will help the company to achieve its objectives and goals foreseen in the company's planning. strategy.

It is essential that the company has a physical, communication and decision-making structure in line with its strategy. Because an organization is a set of integrated systems with a common goal, therefore each element of a company must be aligned and integrated so that its needs are met and it is possible to achieve efficiency, financial advantages and a good competitive position in the market.

On January 1, 2018, Gibson Corporation entered into a four-year operating lease. The payments were as follows: $26,000 for 2018, $20,500 for 2019, $18,000 for 2020, and $14,500 for 2021. What is the correct amount of total lease expense for 2019

Answers

Answer: $19,750‬

Explanation:

The Annual Lease expense is the average of the lease over the 4 year period.

Annual Lease Expense  = Total lease expense / number of years

= (26,000 + 20,500 + 18,000 + 14,500) / 4

= 79,000 / 4

= $19,750‬

Other Questions
Everything in a store is discounted by 25%. What is the sale price of a clock with a regular price of $24.60? Angel Perez describes many students as intent on being perfect. To what extent do his claims apply to you and to your approach to school and life? How would you describe your personal attitude toward perfection and failure? 5. If the area of a rectangular field is 21x - 7x and one of its sides is 7x, what is its other side? Activities that generate external costs will likely be carried out at levels that _____ those that would be efficient. The probability that an online student owns a laptop is 0.82 and the probability that a student owns a desktop is 0.65. If the probability that a student owns both is 0.55, find the probability that a student owns a laptop or a desktop. Where should DoD employees look for guidance on safeguarding classified information? If a company has excess capacity, increases in production level will increase variable production costs but not fixed production costs.a. Trueb. False The poet suggests that goodness and beauty are doubly so when were talking about socks, they are delightful because they come in pairs. Do you think this is a serious remark or a tongue-in-cheek (playful/joking) comment? When two or more firms form a ________ agreement and set price and quantity in unison, economists refer to them as ________. Group of answer choices Identify the part of the website that is being defined. ____ are common questions that users may have about a website I'm having a difficult time with my accounting workbook. I post the adjusting entries, but my balance sheet never equalizes. Can someone point me where i'm going wrong? 1. A supplier shipped $3,000 of ingredients on 12/29/17. Peyton receives an invoice for the goods, as well as a bill for freight for $175, all dated 12/29/17. Goods were shipped FOB suppliers warehouse. 2. At 12/31/17, Peyton has $200 worth of merchandise on consignment at Brunos House of Bacon. 3. On 12/23/17, Peyton received a $1,000 deposit from Pet Globe for product to be shipped by Peyton in the second week of January. 4. On 12/03/2017, a mixer with cost of $2,000, accumulated depreciation $1,200, was destroyed by a forklift. As of 12/23/17, insurance company has agreed to pay $700 in January, 2018, for accidental destruction. 5. Note about later borrowing financials will show loan from parents repaid and use of bank financing.PEYTON APPROVED TRIAL BALANCE As of December 31, 2017 Unadjusted trial balance Adjusting entries Adjusted trial balance Dr Cr ref Dr Cr ref Dr Cr Cash 67,520.04 67,520.04 Accounts Receivable 68,519.91 68,519.91 Other Receivable - Insurance Baking Supplies 15,506.70 15,506.70 Merchandise Inventory 1,238.07 1,238.07 Consignment Inventory Prepaid Rent 2,114.55 2,114.55 Prepaid Insurance 2,114.55 2,114.55 Misc. Supplies 170.49 170.49 Baking Equipment 14,000.00 14,000.00 Accumulated Depreciation 1,606.44 1,606.44 Customer Deposit - Accounts Payable 20,262.11 20,262.11 Wages Payable 3,383.28 3,383.28 Interest Payable 211.46 211.46 Notes Payable 5,000.00 5,000.00 Common Stock 20,000.00 20,000.00 Beginning Retained earnings 50,144.84 50,144.84 Dividends 105,000.00 105,000.00 Bakery Sales 327,322.55 327,322.55 Merchandise Sales 1,205.64 1,205.64 Cost of Goods Sold - Baked 105,834.29 105,834.29 Cost of Goods Sold - Merchandise 859.77 859.77 Rent Expense 24,549.19 24,549.19 Wages Expense 10,670.72 10,670.72 Misc. Supplies Expense 3,000.46 3,000.46 Business License Expense 2,045.77 2,045.77 Misc. Expense 1,363.84 1,363.84 Depreciation Expense 677.86 677.86 Insurance Expense 1,091.08 1,091.08 Advertising Expense 1,549.74 1,549.74 Interest Expense 818.31 818.31 Telephone Expense 490.98 490.98 Gain/Loss on disposal of equipment 429,136.32 429,136.32 - - 429,136.32 429,136.32 LearningDiagnosticAnalyticsSee your levelsWhat is the area of the triangle?7 ft.4 ft.6 ft.square feet On February 1, 2014, Nelson Corporation purchased a parcel of land as a factory site for $280,000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2014. Costs incurred during this period are listed below: Demolition of old building $20,000 Architect's fees 35,000 Legal fees for title investigation and purchase contract 5,000 Construction costs 1,340,000 (Salvaged materials resulting from demolition were sold for $10,000.) Nelson should record the cost of the land and new building, respectively, as:_________. a. $305,000 and $1,365,000. b. $290,000 and $1,380,000. c. $290,000 and $1,375,000. d. $295,000 and $1,375,000. In 1000 sq. meter of land a farmer cultivated 765 kg of rice with the wastage of 23.5%. I) Find the weight of the wastage. II) Find the weight and percentage of rice cultivated. 3) If the area has been increased 40 times in size, how much rice will be cultivated (excluding the wastage) Evaluate online tutorials and online communities in regard to helping users. Create an argument for the approach you find to be the most effective and explain why. What's the area of the following triangle?6 in.10 in.16 in.286 in.14 in.?30 in. J(x) = 220/x^3 and j-x)=220/(-x)^3 he exponential expression 28 has a value of 256. Write two other exponential expressions that have a value of 256. Explain how you got your answers. (Begin by writing out 2 8as the product of 2s.) An electrical heater 150 mm long and 5mm in diameter is inserted into a hole drilled normal to the surface of a large block of material having a thermal conductivity of 10W/mK. The temperature of the electrical heater is 70 oC and the temperature of block surface is 40 oC. Estimate the power dissipation of the electrical heater. (in W) (9x - 4x2 + 9) + (-x3 + 4x2 - 3)