Why is the critical path critical?

Select an answer:
• Any delay in the critical path delays the project finish date.
• It represents tasks in which resources are overallocated.
• It represents tasks that are delayed.
• The tasks on the critical path are the most important ones for achieving the project goal.

Answers

Answer 1

Answer:

Any delay in the critical path delays the project finish date.

Explanation:

The critical path method is also said to be the critical path analysis.

It is referred to a set of algorithm which is used to manage the entire activities related to a project.

The longest activity is identified and the time to complete the activity is measured in a critical path method.

It includes the activities and their time duration to be modeled upon.

In case any of the tasks is delayed, the entire project is delayed.


Related Questions

Trapp Corporation uses the weighted-average method in its process costing system. The beginning work in process inventory in its Painting Department consisted of 3,000 units that were 70% complete with respect to materials and 60% complete with respect to conversion costs. The cost of the beginning work in process inventory in the department was recorded as $10,000. During the period, 10,000 units were started in production and ending work inventory consisted of 4,000 units that 90% complete with respect to material and 85% complete with respect to conversion costs. were If the costs per equivalent unit for the period were $2.00 for material and $3.00 for conversion costs. The cost of units transferred out during the month was:

Answers

Answer:

Total cost of units transferred out= $45,000

Explanation:

The cost of units transferred out would be determined as follows:

Material = cost per unit × Number of equivalent units of units transferred out

Units transferred out = opening inventory + units introduced - closing inventory

= 3,000 + 10,000 - 4,000 = 9,000 units

Material cost = $2×9,000 =             $18,000                

Conversion cost = $3× 9,0000 =     $27,000

Total cost of units transferred out =     $18,000 +$27,000= $45,000

Some people believe that the shuttle should have been better engineered for crew safety, including provisions for repair of the shuttle during the mission, escape of the crew when problems occur during launch, or having a backup shuttle ready to launch for rescue missions. What are some reasons why NASA would not have planned this when the shuttle was designed?

Answers

Answer:

Some of the reasons why NASA would not have planned this when the shuttle was designed was that, they just wanted to launch it by any means and wanted to save cost of launching the space shuttle.

Secondly, the NASA were over confident  that the mission is designed well and is going to come out successfully.

Explanation:

Solution

It is mentioned that some people or individuals that the space shuttle was not  effectively designed and did not carry any provision for crew safety; it did not provide for repair of the shuttle while on a mission; it did not carried anyway round the crew to escape if problems occurs with the space shuttle; and lastly there was no availability of backup space for rescuing this mission.

Some of the reasons why NASA would have not have planned for thus kind of conditions while launching the mission is stated as follows:

The NASA just wanted to launch by any means and also did not want to increase cost of launching this space shuttle by having a back up for the same purpose.

It could also be that the NASA was very confident  and self sufficient that the mission is designed well and is going to be a success. this could be one of the major reasons the NASA did not pay attention towards making provision for the space shuttle mission and it was also a lack of responsibility from the NASA's side that it became over confident and pay no attention towards the safety of the crew going on the mission.

One of the employees of Davenport Corporation recently was involved in an accident with one of the corporation's delivery vans. The corporation is either going to repair the damaged van or sell it as is and buy a comparable used van. Information related to this decision is provided below:

Initial cost of the damaged van $ 30,000
Accumulated depreciation to date on van $ 18,000
Salvage value of van immediately before crash $ 9,000
Salvage value of van immediately after crash $ 1,000
Cost to repair damaged van $ 5,000
Cost of a comparable used van $ 10,000

Based on the information above, Davenport would be financially better off:

Answers

Answer:

Therefore, Davenport would be financially better off by repairing the damaged van for $4,000.

Explanation:

According to the given data in order to calculate how Davenport would be financially better off we would have to calculate the Benefit from repairing damaged van with the following formula:

Benefit from repairing damaged van=Cost of comparable used Van- Repair cost-salvage value before repair after crash

Benefit from repairing damaged van=$10,000 -$5,000 -$1,000

Benefit from repairing damaged van= $ 4,000

Therefore, Davenport would be financially better off by repairing the damaged van for $4,000.

An on-demand printing company has monthly overhead costs of $1,900 in rent, $450 in electricity, $80 for phone service, and $230 for advertising and marketing. The printing cost is $40 per thousand pages for paper and ink. The average cost for printing x thousand pages can be represented by the function C(x) = (2,660+40x) / x. For a given month, if the printing company could print an unlimited number of pages, what value would the average cost per thousand pages approach? What does this mean in the context of the problem? Select one: a. The average cost would approach $0 per thousand pages. The more pages the company prints, the lower the average cost. b. The average cost would approach infinity. The more pages the company prints, the higher the average cost. c. The average cost would approach $40 per thousand pages or equivalently $0.04 per page. This is the cost per page in the absence of fixed costs. d. The average cost would approach $2.660 per thousand pages. This is the total of the fixed monthly costs.

Answers

Answer:

Explanation:

Base on the question been given to us, the solution to the given problem is in the file attached below

Training is a way for eployers to

Provide

to enable employees.

to protect themselves and other injuries

Answers

Answer:

Option B

To enable employees.

Explanation:

Training of employees is usually done by employers, to provide them with basic knowledge they need to perform the job effectively and adequately.

It can also be seen as "enabling" the employees to do the job well. This is because it gives them the right skill sets, mental disposition and information that is necessary to perform their tasks properly.

The following events apply to Lewis and Harper, a public accounting firm, for the 2016 accounting
period:
1. Performed $70,000 of services for clients on account.
2. Performed $40,000 of services for cash.
3. Incurred $36,000 of other operating expenses on account.
4. Paid $10,000 cash to an employee for salary.
5. Collected $47,000 cash from accounts receivable.
6. Paid $16,000 cash on accounts payable.
7. Paid a $8,000 cash dividend to the stockholders.
8. Accrued salaries were $2,000 at the end of 2016.
Required
a. Show the effects of the events on the financial statements using a horizontal statements model like the following one. In the Cash Flow column, use OA to designate operating activity, IA for investment activity, FA for financing activity, NC for net change in cash and NA to indicate the element is not affected by the event. The first event is recorded as an example. (Enter any decreases to account balances and cash outflows with a minus sign.)
a. LEWIS AND HARPER
Statements Model
For Accounting Year 2016
Event No. Assets = Liabilities + Stockholders' Equity Income Statement Statement of Cash Flows
Cash + Accounts Receivable = Accounts Payable + Salaries Payable + Retained Earnings Revenue – Expense = Net Income
1. + 70,000 = + + 70,000 70,000 – = 70,000 NA
2. + = + + – =
3. + = + + – =
4. + = + + – =
5. + = + + – =
6. + = + + – =
7. + = + + – =
8. + = + + – =
Totals + = + + – =
b. What is the amount of total assets at the end of 2016?
c. What is the balance of accounts receivable at the end of 2016?
d. What is the balance of accounts payable at the end of 2016?

Answers

Answer:

Explanation:

Assets Liabilities Income statemment

Event Cash Accounst receivable Accounts Payable Salaries Payable Reatined earnings Revenue Expenses Net Income Statement of Cash Flows

1 $70000 70000 70000 70000 NA

2 40000 40000 40000 40000 40000 OA

3 36000 -36000 - 36000 -36000 NA

4 -10000 -10000 10000 -10000 -10000 OA

5 47000 -47000 0 47000 OA

6 -16000 -16000 0 -16000 OA

7 -8000 -8000 0 -8000 FA

8 2000 - 2000 -2000 NA

Total 53000 23000 20000 2000 56000 110000 0 48000 62000 53000

ans c ans d

Total assets 53000+23000 76000

Atkinson Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Atkinson budgets 2017 assembly-support costs to be $8,800,000 and 2017 direct labor-hours to be 220,000.
At the end of 2017, Atkinson is comparing the costs of several jobs that were started and completed in 2017.
Laguna Model Mission Mode
Construction period Feb-June 2017 May-0ct 2017
Direct material costs $106,550 $127,450
Direct labor costs $36,250 $41,130
Direct labor-hours 970 1,000
Direct materials and direct labor are paid for on a contract basis. The costs of each are known when direct materials are used or when direct labor-hours are worked. The 2017 actual assembly-support costs were $8,400,000, and the actual direct labor-hours were 200,000.
Required:
1. Compute the (a) budgeted indirect-cost rate and (b) actual indirect-cost rate. Why do they differ?
2. What are the job costs of the Laguna Model and the Mission Model using (a) normal costing and (b) actual costing?
3. Why might Atkinson Construction prefer normal costing over actual costing?

Answers

Answer:

Explanation:

Normal costing Actual costing

Assembly support cost $8,800,000 $8,400,000

Direct labor hours 220,000 200,000

Indirect Cost Rate $40 per DLH $42 per DLH

2.

Normal Costing Laguna Model Mission Model

Construction period Feb-June 2017 May-0ct 2017

Direct material costs $106,550 $127,450

Direct labor costs $ 36,250 $41,130

Direct labor-hours 970 1,000

Assmebly support cost $38,800

($40 x 970) $40,000

Total job cost $181,600 $208,580

Actual Costing Laguna Model Mission Model

Construction period Feb-June 2017 May-0ct 2017

Direct material costs $106,550 $127,450

Direct labor costs $ 36,250 $41,130

Direct labor-hours 970 1,000

Assmebly support cost $40,740

($42 x 970) $42,000

Total job cost $183,540 $210,580

Companies now do prefer normal costing than the actual costing, reasons are that the overhead rates are been known from the beginning of the year which is important for giving price estimates and checking the profitability of jobs.

Inventory records for Marvin Company revealed the following:
Date Transaction Number of Units Unit Cost
Mar. 1 Beginning inventory 900 $7.14
Mar. 10 Purchase 560 7.57
Mar. 16 Purchase 790 8.02
Mar. 23 Purchase 510 8.42
Marvin sold 1,900 units of inventory during the month. Cost of goods sold assuming FIFO would be:__________.
(Do not round your intermediate calculations. Round your answer to the nearest dollar amount)
A. $15,998.
B. $14,194.
C. $14,844.
D. $15,155.

Answers

Answer:

B. $14,194.

Explanation:

FIFO means first in, first out. It means that the goods purchased first are the first to be sold.

The 1900 units or inventories sold would be taken from :

1. The beginning inventory = 900 x $7.14 = $6,426

2. Mar. 10 Purchase = 560 x $7.57 = $4,239.20

3. The remaining 440 units of inventory sold would be taken from the Mar. 16 Purchase  = 440 x $8.02 = $3,528.80

Total = $14,194

I hope you

BENETEAU CORPORATION
Comparative Balance Sheet
2017 2016
Assets
Cash $37,000 $31,000
Accounts receivable (net) 80,000 60,000
Prepaid insurance 22,000 17,000
Land 18,000 40,000
Equipment 70,000 60,000
Accumulated depreciation (20,000) (13,000)
Total assets $207,000 $195,000
Liabilities and Stockholder's Equity
Accounts payable $12,000 $6,000
Bonds payable 27,000 19,000
Common stock 140,000 115,000
Retained earnings 28,000 55,000
Total liabilities and stockholder's equity $207,000 $195,000
Additional information:
1. Net loss for 2017 is $12,000. Net sales for 2017 are $250,000.
2. Cash dividends of $15,000 were declared and paid in 2017.
3. Land was sold for cash at a loss of $2,000. This was the only land transaction during the year.
4. Equipment with a cost of $15,000 and accumulated depreciation of $10,000 was sold for $5,000 cash.
5. $12,000 of bonds were retired during the year at carrying (book) value.
6. Equipment was acquired for common stock. The fair value of the stock at the time of the exchange was $25,000
Required:
1. Prepare a statement of cash flows for the year ended December 31, 2017, using the indirect method.

Answers

Answer:

A cash flow statement  for the year ended December 31, 2017,using indirect method was prepared for BENETEAU CORPORATION.

Explanation:

Solution

Prepare the cash flow statement using indirect method as follows:

Statement of cash flows for the year ended December 31, 2017, using the indirect method.

B Corporation

Statement of Cash Flows  For the Year Ended December 31, 2017

Cash flows from operating activities:

Net loss=-12000

Adjustments to reconcile net loss with cash flows from operating activities:

Depreciation ($20,000 + $10,000 - $13,000) = 17000

Loss on sale of land = 2000

Increase in accounts receivable= -20000

Increase in prepaid expenses=-5000

Increase in accounts payable=6000

Net cash used in operating activities=-12000

Cash flows from investing activities:

Sale of land ($40,000 - $18,000 - $2,000) =20000

Sale of equipment =5000

Net cash generated by investing activities =25000

Cash flows from financing activities:

Retirement of bonds=-12000  

Proceeds from issuance of bonds=20000  

Dividends paid=-15000

Net cash used by financing activities=-7000

Net increase in cash=6000

Add: Beginning cash balance=31000

Ending cash balance=37000

Now:

(1) The Calculation of Depreciation:

The accumulated Depreciation at end of 2017 = $ (20,000)

Thus,

Accumulated Depreciation at end of 2017 = $ (13,000)

Increase in Accumulated Depreciation during 2017 = 20,000 - 13,000 = $ 7,000

Add: Accumulated depreciation on equipment sold during 2017 = $ 10,000

Total Depreciation expense for 2017 = $ 7,000 + 10,000 = $ 17,000

(2) Calculation of Proceeds from the sale of land:

The land cost sold = $ 40,000 - 18,000 = $ 22,000

The sale of the loss of land  = $ 2,000

Hence,

Proceeds from sale of land = Cost of land sold - Loss on sale of land = $ 22,000 - 2,000 = $ 20,000

(3) Calculation of Issuance of bonds payable during 2017

The Bonds Payable at the end of 2016 = $ 19,000

So,

Bonds Payable at the end of 2017 = $ 27,000

Retirement of bonds during 2017 = $ 12,000

Bonds issued during 2017 = $ 27,000 + 12,000 - 19,000 = $ 20,000

Now,

(a) Calculation of Current cash debt Coverage times:

Current cash debt Coverage times = Net cash provided by operating activities / Average current liabilities

Provision of net cash operating activities = ($12,000)

The current average  liabilities = (Opening current liabilities + Closing current liabilities) / 2

= (12,000 + 6,000) / 2 = $ 9,000

Current cash debt Coverage times = ($12,000) / $ 9,000 = -1.33 times

(b) Calculation of Cash debt coverage times:

Cash debt coverage times = Net cash provided by operating activities / Average total liabilities

Thus,

Net cash provided by operating activities = ($12,000)

Average Total liabilities = (Opening Total liabilities + Closing Total liabilities) / 2

= ($ 25,000 + 39,000) / 2 = $ 32,000

Therefore, the cash debt coverage times = ($12,000) / $32,000 = -0.375 = -0.38 times

Agricultural output is affected by the weather. Excessively high temperatures and a lack of rainfall are detrimental too crop yields. Of course, all farmers want the best growing conditions possible, and they work with whatever the weather is, in order to maximize their crop yield. Suppose, however, for a particular crop, this is a bad year and there is a decrease in crop yield, and therefore less of the good is produced. Is there any way this could be beneficial for the framersrevenue? a) Without the use of a diagram, in your own words, layout the conditions) under which this could happen b) Suppose you have a bright but sceptical friend who doubts your answer in part (a). Without relying on technical jargonexplain (again, in your own words) how such a surprising result is possible

Answers

Answer: The answer is provided below

Explanation:

a. When the quantity supplied of a particular crop reduces, it will affect the farmer's revenue but this can still be beneficial to the farmer provided these conditions prevails:

• If demand for the crop rises more than its fall in supply, this will lead to a rise in the and price of the crop. Hence, there will also be an increase in the revenue of the farmer and the farmer will try to adjust output and sell at higher prices. Therefore, the excess demand can off set a fall in the supply.

b. We know that the supply of a crop is limited. For example, let's assume that the crop is rice. Now the situation is that people are demanding more beans maybe as a result of festive season. Therefore, everyone will want to purchase rice which will lead to an increase in the price of rice due to excess demand.

The farmer will try as much as possible to maximise profit and will therefore sell the rice at higher price to those that wants to buy. Therefore, it's clear that the farmer can still benefit, even if his supply is limited, but the demand must be greater than its decline in supply.

Jake wants to purchase a new computer and go to the Caribbean for spring break. The computer is priced at $1,299, and the vacation is priced at $800. He has only $1,574 in his checking account, so he cannot afford to purchase both. After much thought, Jake buys the computer and writes a check for $1,299.
Identify what role money plays in each of the following parts of the story.
Hint: Select each role only once.
Role of Money
Medium of Exchange
Unit of Account
Store of Value
Jake can easily determine that the price of the computer is more than the price of the vacation.
Jake has $1,574 in his checking account.
Jake writes a check for $1,299.

Answers

Answer:

1. Jake can easily determine that the price of the computer is more than the price of the vacation.  ⇒ UNIT OF ACCOUNT

2. Jake has $1,574 in his checking account.  ⇒ STORE OF VALUE

3. Jake writes a check for $1,299. ⇒ MEDIUM OF EXCHANGE

Explanation:

The four functions of money are:

unit of account: since money is a common denominator, it helps to assign value to different goods and services.store of value: you can save money in order to purchase gods and services in the future.medium of exchange: you can purchase and sell goods and services using. moneystandard of deferred payment: money allows loans that require future payments of both principal and interest.

Deluxe Building Services offers custodial services on both a contract basis and an hourly basis. On January 1, 2015, Deluxe collected $30,150 in advance on a six-month contract for work to be performed evenly during the next six months. Assume that Deluxe closes its books and issues financial reports on a monthly basis.
a. Prepare the entry on January 1 to record the receipt of $30,150 cash for contract work (1) using the financial statements effect template and (2) in journal entry form.
b. Prepare the adjusting entry to be made on January 31, 2015, for the contract work done during January (1) using the financial statements effect template and (2) in journal entry form.
c. At January 31, a total of 30 hours of hourly rate custodial work was unbilled. The billing rate is $19 per hour. Prepare the adjusting entry needed on January 31, 2015, (1) using the financial statements effect template and (2) in journal entry form. (The firm uses the account Fees Receivable to reflect amounts due but not yet billed).

Answers

Answer:

Since there is not enough room here, I prepared the financial statement effects template on an excel spreadsheet that I attached.

a)

January 1, unearned revenue

Dr Cash 30,150

    Cr Unearned service revenue 30,150

b)

January 31, accrued services

Dr Unearned service revenue 5,025

    Cr Service revenue 5,025

c)

January 31, service revenue from hourly custodial work

Dr Accounts receivable 570

    Cr Service revenue 570

Financial Statement Notes: Quarterly Data Quarterly data are presented below for Company A and Company B. One of these companies is Gibson Greetings, Inc., which manufactures and sells greeting cards. The other company is Hon Industries, Inc., which manufactures and sells office furniture. Both companies are on a calendar year basis. (Amounts in Thousands) First Quarter Second Quarter Third Quarter Fourth Quarter Year Company A Net sales $186,111 $177,537 $203,070 $213,608 $780,326 Gross profit 55,457 53,643 64,024 69,374 242,498 Company B Net sales $84,896 $83,796 $142,137 $235,336 $546,165 Gross profit 53,900 52,983 66,018 104,961 277,862 Required a. Compute the percent of annual net sales generated each quarter by Company A. Round to the nearest percent. b. Compute the percent of annual net sales generated each quarter by Company B. Round to the nearest percent.

Answers

Answer and Explanation:

The computation of percent of annual net sales generated each quarter by Company A and B is shown below:-

                                   First        Second           Third          Fourth

                                    Quarter    Quarter          Quarter       Quarter

a. Company A annual

net sales percentage    24%         23%               26%            27%

($186,111 ÷ $780,326) ($177,537 ÷ $780,326) ($203,070 ÷ $780,326) (213,608 ÷ $780,326)

b. Company B annual

net sales percentage     16%           15%               26%           43%

($84,896 ÷ $546,165) ($83,796 ÷ $546,165) ($142,137 ÷ $546,165) ($235,336 ÷ $546,165)

So, for computing the percent of annual net sales generated each quarter by Company A and B we simply divide the Net sales of every quarter by Net sales of Year same for Company B.

a. The computation of the percent of annual net sales by Company A are as follows:

Quarter 1 = 24% ($186,111/$780,326 x 100)      

Quarter 2 =23% ($177,537/$780,326 x 100)

Quarter 3 = 26% ($203,070/$780,326 x 100)

Quarter 4 = 27% ($213,608/$780,326 x 100)

b. The computation of the percent of annual net sales by Company B are as follows:

Quarter 1 = 16% ($84,896/$546,165  x 100)      

Quarter 2 =15% ($83,796/$546,165  x 100)

Quarter 3 = 26% ($142,137/$546,165  x 100)

Quarter 4 = 43% ($235,336/$546,165  x 100)

Data and Calculations:

(Amounts in Thousands)

                   First Quarter Second Quarter Third Quarter Fourth Quarter Year

Company A:

Net sales         $186,111          $177,537          $203,070      $213,608 $780,326

Gross profit      55,457              53,643              64,024          69,374     242,498

Company B:

Net sales       $84,896           $83,796            $142,137     $235,336    $546,165

Gross profit     53,900             52,983               66,018         104,961      277,862

Learn more: https://brainly.com/question/15418611

Based on the following information: Assume that Forrest Company uses the LIFO accounting method. In year X1, Forrest reported the following information:
Units Unit Cost Total Cost
Beginning Inventory (1/1/X1) 1,000 10 10,000
Purchases (year X1) 2,000 11 22,000
Year X1 Sales 1,500
Ending Inventory (12/31/X1) 1,500
Based on the above information, Forrest Company will report which of the following amounts for its LIFO Inventory on 12/31/X1?
a. $15,500
b. $16,000
c. $16,500
d. none of the above.

Answers

Answer:

a. $15,500

Explanation:

Based on LIFO, cost of 1500 unit sold will be entirely from the Purchases (year X1). Therefore, we have:

Value of units purchases (year X1) outstanding after sales = (2,000 - 1,500) * $11 = 500 * $11 = $5,500

Therefore, we have

LIFO Inventory on 12/31/X1 = Value of beginning Inventory (1/1/X1) + $5,500 = $10,000 + $5,500 = $15,500.

What is implied by the fact that in today’s marketplace, the volume of world trade has been growing faster than world GDP? more companies are relying on domestic firms to obtain parts of their production process the economies of the world’s nation-states are becoming less intertwined more companies are dispersing parts of their production process to locations around the globe the world has experienced a loss of overall wealth in the last two decades more countries are imposing trade barriers to minimize competition

Answers

Answer:

The correct answer is: more companies are dispersing parts of their production process to locations around the globe.

Explanation:

It is correct to say that the volume of world trade in the current market has been growing faster than world GDP due to the fact that globalization is a phenomenon that has narrowed trade relations between countries due to greater ease of communication and reduced transport costs. .

Therefore, nations are becoming more interconnected due to the union of a global market that reduces the commercial borders between countries and makes them increasingly dependent for the commercial transaction of products and services.

There are several benefits added to globalization, such as developing countries and markets, increasing jobs, and the possibility of reducing production costs using the strategy of transferring parts of the production process to countries with cheaper labor and less bureaucratization, in order to reduce costs and increase product quality.

During the taking of its physical inventory on December 31, 2013, Waterjet Bath Company incorrectly counted its inventory as $728,660 instead of the correct amount of $719,880. Indicate the effect of the misstatement on Waterjet Bath's December 31, 2013, balance sheet and income statement for the year ended December 31, 2013. Also record the amount of each overstatement or understatement. Enter all amounts as positive numbers.

Answers

Answer and Explanation:

Since in the question it is mentioned that

Incorrectly amount recorded = $728,660

And, the corrected amount is = $719,880

The difference is

= $728,660 - $719,880

= $8,780

Based on the misstatement, the effect on the financial statement is

For Balance sheet:

Overstatement of Merchandise inventory = $8,780

Overstatement of Current assets = $8,780

Overstatement of Total assets = $8,780

Overstatement of Owner equity = $8,780

For Income statement:

Understatement of Cost of merchandise sold = $8,780

Overstatement of Gross profit = $8,780

Overstated of Net income = $8,780

The following transactions occur for the Panther Detective Agency during the month of July:
a. Purchase a truck and sign a note payable, $15,000.
b. Purchase office supplies for cash, $600.
c. Pay $800 in rent for the current month.
Required:
1. Record the transactions. The company uses the following accounts: Cash, Supplies, Equipment (for the truck), Notes Payable, and Rent Expense. (If no entry is required for a transaction/event, select "No Journal Entry Required" in the first account field.)

Answers

Answer:

a.

Dr Equipment $15,000

Cr Notes payable $15,000

b.

Dr Supplies $600

Cr Cash $600

c.

Dr Rent expense $800

Cr Cash $800

Explanation:

Panther Detective Agency Journal entry

a.

Dr Equipment $15,000

Cr Notes payable $15,000

b.

Dr Supplies $600

Cr Cash $600

c.

Dr Rent expense $800

Cr Cash $800

Answer:

Panther Detective Agency

Journal Entries:

a) Debit Equipment Account $15,000

Credit Notes Payable $15,000

To record purchase of truck with a note.

b) Debit Supplies Account $600

Credit Cash Account $600

To record purchase of office supplies for cash.

c) Debit Rent Expense $800

Credit Cash Account $800

To record payment of rent for the current month.

Explanation:

a) The purchase of a truck increases the Equipment Account and the Notes Payable Account by $15,000.

b) Payment for office supplies reduces the Cash Account and increases the Supplies Account by $600.

c) The payment for rent for the current month increases the Rent Expense Account and reduces the Cash Account by $800.

d) The use of journal entries is to record business transactions as they occur.  It makes it easier to know which account will be credited and which to be debited in the Ledger.

g During fiscal 2011, we repurchased with cash (i.e., bought) 2 million shares of common stock for an aggregate purchase cost of $700 million. We reissued (i.e., sold) 5 million shares of common stock held in treasury for $2000 million in cash during fiscal 2011. The cost basis of the 5 million shares of treasury stock reissued is $300 per share. What journal entries did ALM record in its treasury stock transactions in 2011

Answers

Answer:

Dr. Treasury Stock $700 million

Cr.  Cash                 $700 million

Dr.  Cash                                          $2,000 million

Cr. Add-in-Capital Treasury Stock $500 million

Cr. Treasury Stock                          $1,500 million

Explanation:

Treasury stocks are the company's own shares which is repurchased by the company. It is recorded in treasury shares account which is an contra equity account. I can be reissued or cancelled by the company.

Purchase of Treasury Stock

Treasury Stock = $700 million

Sales of Treasury Stock

Cash Receipt = $2,000

Treasury Stock = 5 million x $300 = $1,500

Paid-in capital - Treasury stock = $2,000 - $1,500 = $500

IZ Corporation purchased land for $400,000. Later in the year, the company sold a different piece of land with a book value of $200,000 for $240,000. How are the effects of these transactions reported on the statement of cash flows assuming the indirect method is used? Use the minus sign to indicate cash out flows, cash payments, decreases in cash and for any adjustments, if required. If a transaction has no effect on the statement of cash flows, select "No effect" from the drop down menu and leave the amount box blank.

Answers

Answer and Explanation:

1. Gain on sale of land

It is come from

= Sale value - book value

= $240,000 - $200,000

= $40,000

Since there is a gain of $40,000 which is to be deducted from a net income under the cash flow from operations

2. Cash received from sale of land

The cash is received from sale of land reflects that the cash is come i.e inflow of cash and the same is to be reflected under the cash flow from investing activities in a positive amount i.e $240,000

3. Cash paid for purchase of land

The cash is paid for purchase of land reflects that the cash is gone i.e outflow of cash and the same is to be reflected under the cash flow from investing activities in a negative amount i.e -$400,000

Answer:

Gain on Sale of Land: (Deducted from net income) $ - 40,000

Cash Received from Sale of Land: (Part of cash flows from investing activities) $ 240,000

Cash Paid for Purchase of Land: (Part of cash flows from investing activities)  $ - 400,0000

Explanation:

ABC Corporation has declared a rights offering to stockholders of record on Friday, December 10th. Under the offer, shareholders need 10 rights to subscribe to 1 new share at a price of $19. Fractional shares can be rounded up to purchase 1 full share. As of the ex date, the stock is trading at $29. The value of the right is:

Answers

Answer:

The value of a right is $1

Explanation:

10 rights are needed to buy 1 share at the price of $19

Value of total rights = $29 - $19 =$10

Value of a right = [tex]\frac{10}{10}[/tex] = $1

Sheridan Co. incurred research and development costs in 2021 as follows: Materials used in research and development projects $ 915000 Equipment acquired that will have alternate future uses in future research and development projects 2650000 Depreciation for 2021 on above equipment 441666 Personnel costs of persons involved in research and development projects 715000 Consulting fees paid to outsiders for research and development projects 265000 Indirect costs reasonably allocable to research and development projects 190000 $5176666 The amount of research and development costs charged to Sheridan's 2021 income statement should be a. $2071666. b. $1895000. c. $2526666. d. $4545000.

Answers

Answer: c. $2,526,666.

Explanation:

When calculating amount of research and development costs charged to Sheridan for 2021, the concern should be for period costs i.e, costs that are incurred for 2021 alone. Therefore the Equipment cost cannot be put here because as an Asset it was purchased for future use and so cannot be just for 2021.

The costs therefore are all of the above EXCEPT cost.

= Materials + Depreciation + Personnel Costs + Consulting fees + Indirect Costs

= 915,000 + 441,666 + 715,000 + 265,000 + 190,000

= $2,526,666

Correct answer is Option C

Tung is nearly fifty years of age and has not had a job for the past twenty-five years. He holds a bachelor's degree in engineering and is in good health. When he casually discusses his lack of employment with friends, he tells them "there are no jobs out there," "no one wants to pay me what I'm worth," or "I was offered a job but it's too far to travel."
1. Based on this scenario, which statement best explains Tung's lack of a job?

Answers

Answer:

1- Tung is a exemple of the ideology of personal responsability.

Explanation:

The ideology of personal responsibility corresponds to a set of personal ideologies about the facts that happen in your life.

The individual believes that everything that happens is because of his actions and therefore occurs because of his own cause and choice. Therefore, they believe that because they choose their actions, they should be held responsible for them both legally and morally.

An aircraft manufacturer with a strong presence in the United States, is looking to expand its market overseas. The firm currently sells its aircraft to several airlines in the United Kingdom but now wants to establish manufacturing units there as well in order to acquire a bigger share in the European market. Hence, it plans to merge with QueenAir, a British aircraft manufacturer. Which of the following, if true, would weaken the company's decision to merge with QueenAir?

a. Merging with QueenAir would increase its profits considerably.
b. There is increasing economic uncertainty in its U.S. market.
c. The preferences of airline customers in Europe and the U.S. are similar.
d. There is a striking difference in the organizational cultures of the two firms.
e. A competitor in the U.S. market recently went out of business.

Answers

Answer:

d. There is a striking difference in the organizational cultures of the two firms.

Explanation:

Numeral d would likely be the argument that would weaken the company's decision to merge with QueenAir.

The reason is that, if the two companies have strikingly different organizational cultures (for example, the American company could have a more traditional, vertical hierarchy, while the British company could be more horizontal and less hierarchical), coordinating them both once the merge is completed could be so difficult as to make the whole process not worth it.

Presented below is the information for Irvine Corp.: Irvine Corp.. has prepared the following comparative balance sheets for 2020 and 2021: 2021 2020 Prepaid expenses 1,800 2,700 Cash 28,200 15,300 Accounts receivable 13,900 17,000 Inventory 36,500 26,000 Patent 15,300 17,400 Plant assets 129,500 105,000 Accumulated depreciation -45,000 -37,500 180,200 145,900 Accounts payable 15,300 16,800 Accrued liabilities 6,000 4,200 Mortgage payable 0 58,300 Additional Paid In Capital 12,000 0 Preferred stock 74,000 Common Stock 60,000 60,000 Retained earnings 12,900 6,600 180,200 145,900 The income statement for 2021 is as follows: Sales revenue $198,000 Cost of sales 108,900 Gross profit 89,100 Operating expenses 69,000 Net income $20,100 Other Facts: Included in operating expenses: Depreciation Expense 7500 Vehicle expense 2800 Interest Expense 15600 Gain on Sale of Asset 5000 Pension Contribution 7500 Other: Dividends 13800 Cash Rec'd From Sale of Assets 35000 Basis of Assets Sold 30000 PREPARE A PERFECT CASH FLOW STATEMENT

Answers

Answer:

Hey hey hey hey hey

Explanation:

The Bella Capri runs as an Italian restaurant that specializes in freshly prepared cooked meals. It is located in premises on a main street of town with seating capacity for 45 customers. The lease on the premises is $250 per week. General business expesnes are a further $150 each week. Light, heat and fuel are $40 per week. Wage costs for three staff (cook and two waiters) is $600 per week including all other employment costs. The restaurant has set their prices so that it is possible to buy a meal for around $16 per head on average. The cost of the ingredients would be no more than $4 per head. What will be the fixed costs for Bella Capri per week

Answers

Answer:

The answer is $1000.

Explanation:

We can define fixed cost as the costs that does not increase or decrease as with the change in the service given or the goods produce.

According to this, we can say that the $16 price per meal and therefore the $4 ingredients are not included in the fixed cost. The light, heat and fuel are also dependent on the usage, so they do vary with the service given.

The other costs given in the question are eligible to be counted as fixed costs because they are not dependent on the number of costumers or the amount of food served.

So the fixed costs for Bella Capri per week is $250 + $150 + $600 = $1000.

I hope this answer helps.

What can be a cost of opening a basic checking account?


high interest rates


penalties for early withdrawal


check writing limits


high fees

Answers

Answer: High Fees

Explanation:

Checking accounts are very useful to the common person because of the liquidity they offer. With a Checking account, you are able to make withdrawals whenever you want by way of checks or ATM cards as many times as you want. Electronic transfers are available and depositing is quite simple.

In exchange for this high Liquidity though, the account receives low interest and can be subject to quite a number of fees.

Depending on the bank there are different fees attached with some of the most common being, Card processing fees, electronic and mobile banking fees, Overdraft fees, Maintenance fees and sometimes even a fee for letting the account drop below a minimum value.

The CORRECT ANSWER is "check writing limits" I just took the test:) Hope this helps

Vaughn Manufacturing reported net income of $471000 for the year ended 12/31/21. Included in the computation of net income were: depreciation expense, $59600; amortization of a patent, $32200; income from an investment in common stock of Ivanhoe Company, accounted for under the equity method, $48500; and amortization of a bond discount, $12700. Vaughn also paid an $79000 dividend during the year. The net cash provided by operating activities would be reported at _________.

Answers

Answer:

$483,800

Explanation:

Prepare the Cash flow from Operating Activity Section as follows :

Net Income for the year                             $471,000

Adjustments for Non-cash items :

Depreciation expense                                $59,600

Amortization of a patent                             $32,200

Cash Generated from Operations           $562,800

Dividend Paid                                             ($79,000)

Net Cash from Operating Activities         $483,800

Marin Company leased equipment from Costner Company, beginning on December 31, 2019. The lease term is 8 years and requires equal rental payments of $56,394 at the beginning of each year of the lease, starting on the commencement date (December 31, 2019). The equipment has a fair value at the commencement date of the lease of $350,000, an estimated useful life of 8 years, and no estimated residual value. The appropriate interest rate is 8%.

Required:
Prepare Marin's 2019 and 2020 journal entries, assuming Marin depreciates similar equipment it owns on a straight-line basis.

Answers

Answer and Explanation:

The journal entries are shown below:

1. Right of use assets$350,000      ($56,394 × 6.2064)

           To lease liability  $350,000

(Being the lease liability is recorded)

Refer to the present value annuity due factor table for 6.2064

2. Lease liability $56,394

        To cash $56,394

(being cash paid is recorded)

3. Lease liability $32,905

   Interest expense  $23,489    {($350,000 - $56,394) × 8%}

            To Cash   $56,394

(Being cash paid is recorded)  

4. Amortization expense $43,750   {$350,000 ÷ 8 years)

         To Right of use asset $43,750

(Being the amortization expense is recorded)

Fred was suffering from a nasal tissue blockage that could be corrected either through an operation or with medical treatment for about two months. Fred's doctor clearly told him that the condition was not acute and he did not need surgery. Fred, however, insisted on the surgical removal of the blockage, being aware that his medical insurance would cover the entire cost of this surgery. The situation described here can be associated with which of the following problems? A) Price dispersionB) Moral hazardC) Lemons problemD) Prisoner's dilemma

Answers

Answer:

The correct answer to the following question will be Option B (Moral hazard).

Explanation:

Moral hazard happens whenever one individual takes further chances as the responsibility of such consequences rests with somebody else.

Fred suffered from some kind of blockage of the nasal tissues that could have been resolved for around 2 months either by a procedure and via medical attention. Fred's doc warned him plainly the problem wasn't serious so he doesn't need an operation.However, Fred concentrated on either the blockage becoming surgically removed, becoming mindful that his private policy would fund the full cost of this operation.

The other given options are not related to the given scenario. So that the condition outlined here could be related to the "Moral hazard" issue.

The higher education department of Holmes Institute recorded data on the number of students enrolled in the different study majors for the years Study Major 2018 2019 Statistics 1700 2250 Business Law 700 900 Accounting 1300 1450 Economics 750 1000 Finance 1450 1758 Marketing Management 1069 1189 Auditing 360 3512018 and 2019. The data are stored in file STUDYMAJOR.xls. a) Use an appropriate graphical technique or chart to compare the number of enrolment in 2018 and 2019 of the different study major. Display the chart. (2 marks) b) Use an appropriate graphical technique or chart to display the percentage value of the number of enrolment of the different study major in 2018 and 2019. Display the chart.

Answers

Answer:

The number of enrolment and the calculated the percentage value of the number of enrolment of the different study major in 2018 and 2019 are given below:

Study Major                            2018    2019        2018 (%)  2019 (%)

Statistics                              1,700     2,250              23%    25%

Business Law                        700        900              10%     10%

Accounting                          1,300      1,450              18%    16%

Economics                             750      1,000               10%     11%

Finance                               1,450       1,758              20%    20%

Marketing Management    1,069       1,189                15%     13%

Auditing                                 360         351                 5%      4%

Total                                    7,329      8,898           100%    100%

Explanation:

Note: See the attached excel file for the two bar charts.

Other Questions
40 PTS!!How many possible outcomes exist when four fair coins are flipped? 2 4 8 16 3 - 40 30+ 20whats x? geometry angles!!! What is the name of the system of measurement used by most countriesaround the world? About how many inches wide is the toolbox? [tex]7.2 in. \: gum \: wrappers[/tex][tex]12.49in. \: shoelaces [/tex][tex]4.579in. \: paperclips[/tex]Answer FAST PLS!!!!! Will records the wins and losses for his high school basketball team each year. He notices that the ratio of wins to losses hasbeen consistent each year,VXWinsLosses18245536427XUsing the information in the table, how many losses should he predict for next year if the number of games won is 2721369Save and ExitNextSubmitMark this and return What is the percent of change in the cost of a DVD set that originally sold for$69.99 and is now on sale for $44.99? Round your answer to the nearest whole number. Will mark as brainliest if correct who developed the heliocentric model What were the reasons for the collapse of the Sui, Tang, and Song dynasties? 29. A state with Oklahoma on its north and New Mexico on its west? As time went on, the number of troops in Vietnam Write an addition equation or a subtraction equation to describe the diagram A figure is translated . Which translation will move the image back to thepreimage original position? Make a claim about whether a mirrors surface is transparent, translucent, or opaque.Summarize evidence to support the claim and explain your reasoning. Ana Patricia ________ en Mxico. vivo vive viven vives Express the required calculation in terms of it and then round to the nearest tenth.How much fencing is required to enclose a circular garden whose radius is 20 meters?There are of fencing required.(Simplify your answer. Type an exact answer in terms of 7.)There are approximatelyof fencing required.(Round to the nearest tenth as needed.) Look on my last post giving 70 points for one math problem if u answer I will rate u brainiest on this question and on that one "What is the theoretical probability of rolling a prime number on a standard number cube?" What is the length of a radius of the circle represented by the equationx2 + y2 - 4x - 4y + 4 = 0?A) 2 unitsB) 4 unitsC) 8 unitsD) 16 units